GDS Nusajaya Tech Park Data Center Campus
Đang hoạt độngNusajaya Tech Park, Iskandar Puteri, Johor, Malaysia
Hyperscale campus at Nusajaya Tech Park, Johor, designed for about 22,500 sqm of net floor area and 54 MW of IT power; Phase 1 started operations in July 2023.
Nhà vận hành
GDS Holdings
Thành phố
Iskandar Puteri, Malaysia
Công suất, MW
54 MW
Cooling
Air
Opened
2023
Floor space
22,500 m²
GDS picked Nusajaya Tech Park in Iskandar Puteri, Johor, for its first data centre outside China, and the campus opened formally on 10 August 2023. Phase one comprises the NTP1-3 buildings with a combined net floor area of about 22,500 sqm; company plans describe roughly 54 MW of IT power for the campus at full build. The first building was delivered in around 14 months using GDS's prefabricated Smart DC construction approach, which the operator credits for both speed and energy efficiency, and the overall investment was reported at more than RM1 billion. Location is the campus's core argument: it sits minutes from the Second Link crossing to Singapore, letting hyperscalers and large enterprises land capacity that is constrained or costly on the island while keeping latency to Singapore low. Green design features and low-carbon operation are baked into the campus concept. It anchors GDS International's (now DayOne) Johor-Singapore-Batam platform strategy.
- ▮First GDS data centre campus outside China; grand opening August 2023
- ▮Phase 1 (NTP1-3) totals ~22,500 sqm net floor area
- ▮Campus planned for roughly 54 MW of IT power
- ▮NTP1 delivered in ~14 months via prefabricated Smart DC construction
- ▮Located at Nusajaya Tech Park, Iskandar Puteri, near the Singapore Second Link