NTT Cyberjaya Campus, Cyberjaya, Selangor, Malaysia

7 MW critical IT load data centre on NTT's Cyberjaya campus, built with an investment of over RM234 million and using cooling-wall technology for racks up to 15 kW.

运营商

NTT Global Data Centers

城市

Cyberjaya, 马来西亚

电力, MW

7 MW

Cooling

Air

Opened

2023

Floor space

4,890 m²

Max density

15 kW/rack

Launched in October 2023 after a construction start in September 2022, CBJ6 rounded out NTT's Cyberjaya campus as its sixth building, adding 7 MW of critical IT load and about 4,890 sqm of space for an investment of over RM 234 million (around USD 50 million). The engineering mirrors the formula proven in the neighboring CBJ5: advanced cooling-wall technology keeps a stable environment for racks up to 15 kW, and two 33 kV substations provide diverse power reception. Together the two newest buildings give the campus roughly 20,000 sqm of combined space and a 22 MW facility load, making it one of the larger established colocation footprints in Cyberjaya, Malaysia's original data-center district. NTT positions the campus at the crossroads of its submarine cable investments through Malaysia, which appeals to carriers and cloud platforms as well as domestic enterprises. CBJ6 is a fit for organizations that want capacity in the Klang Valley on a mature, multi-building campus rather than a greenfield hyperscale park in Johor.

  • 7 MW critical IT load, launched October 2023
  • About 4,890 sqm of space; racks up to 15 kW via cooling-wall technology
  • Investment of over RM 234 million (~USD 50 million)
  • Two 33 kV substations with diverse power reception
  • Campus with CBJ5 totals ~20,000 sqm and 22 MW facility load